How to Calculate Concrete for a Slab

Published on:

September 29, 2026

A concrete slab calculator answers one question: how many cubic metres does this slab consume. That is multiplication, and it takes seconds. The number that matters on site is different. It is how much concrete to order, which is the calculated volume plus everything the calculation leaves out.

This guide covers both. Run the calculator for the theoretical figure, then work through what sits outside it, so the truck that arrives carries the right volume the first time.

The formula, and the calculator

Concrete volume is area multiplied by depth. Express the depth in metres and the answer comes out in cubic metres, which is how concrete is batched, sold and delivered.

Volume (m³) = length (m) × width (m) × thickness (m)

A 10 metre by 8 metre slab at 100 mm gives 10 × 8 × 0.1, which is 8 cubic metres. Nothing about that changes with slab size or site.

Step one: measure the slab area accurately

Rectangular slabs

Measure the slab footprint, not the building footprint. They are not always the same once you account for the slab edge, and a 100 mm discrepancy carried around a perimeter adds up.

Work from the structural drawings rather than a tape across the pad. Set-out errors get built into the volume before anyone orders anything.

Irregular and stepped footprints

Break the shape into rectangles, calculate each one separately, then add them. This is faster and less error prone than trying to treat an L-shaped or stepped slab as a single figure.

Where the slab steps down in thickness across the footprint, treat each thickness zone as its own calculation. Averaging the thickness across a stepped slab is one of the more common ways a pour comes up short.

What to include and exclude at the edges

Slab edges rarely stop at the line on the plan. Rebates, set-downs at door thresholds, upstands and thickened edges all sit outside a simple length by width figure.

Mark them on the drawing before you start measuring, and calculate each one as a separate volume.

Step two: confirm the design thickness, do not assume it

Thickness is not a builder's choice. The engineer sets it against the site classification, the imposed loads and the slab system.

A 150 mm slab consumes half again the concrete of a 100 mm slab over the same area, so the thickness the engineer specifies moves the order more than any other single input. A 20 mm error on a 150 mm slab is a 13 per cent volume error, which on a large pour is the difference between finishing and calling for a second truck.

Read the thickness off the footing and slab plan, not the architectural drawings.

Step three: convert area and thickness into cubic metres

Thickness is specified in millimetres and volume is sold in cubic metres, so the conversion is where most arithmetic errors happen. Divide millimetres by 1,000 to get metres before you multiply.

Each square metre of slab consumes a volume equal to its thickness in metres. That gives a shortcut worth memorising:

Nominal slab thickness Volume per square metre Relative to 100 mm
100 mm 0.10 m³ 1.0x
125 mm 0.125 m³ 1.25x
150 mm 0.15 m³ 1.5x
175 mm 0.175 m³ 1.75x
200 mm 0.20 m³ 2.0x
250 mm 0.25 m³ 2.5x

Multiply your slab area by the figure in the middle column and you have the theoretical volume without touching a calculator.

Step four: add the beams, thickenings and edge details

Excavated edge beam with reinforcement cage in place around a slab perimeter

A slab on ground is not a flat plate. Edge beams, internal beams and thickenings under load-bearing walls all sit below the nominal slab thickness, and every one of them consumes concrete the flat calculation does not account for.

Take the beam dimensions from the footing plan, calculate each beam as length by width by depth, and add them to the slab figure. Where beams intersect, count the overlap once rather than twice.

On a typical stiffened raft slab the beams are a material share of the total pour, not a rounding error. Skipping them is the most expensive mistake on this list.

Step five: adjust for slab type

Slab on ground

Flat slab volume plus beams and thickenings, as above. The calculation is additive and straightforward.

Waffle pod raft slabs

Waffle pods laid out in a grid with reinforcing mesh over the top before a slab pour

Pods displace concrete, so here the calculation is subtractive as well as additive. Work out the volume of the slab envelope, then deduct the volume the pods occupy, then add the ribs and edge beams back in.

Pod dimensions and spacing come from the slab layout drawing. Two waffle slabs with the same footprint and different pod layouts do not consume the same concrete.

Post-tensioned slabs

Volume is calculated the same way, but the pour sequence and the stressing programme change how the volume is delivered and when. The tendons, ducting and anchorages occupy space that a straight geometric calculation ignores.

Post-tensioned pours are also less forgiving of running short mid-pour, because a cold joint in the wrong place is a design problem rather than a finish problem.

Step six: add an allowance before you order

The theoretical volume assumes the excavation is exactly to level, the formwork does not move, and nothing is lost between the truck and the slab. None of that holds.

An allowance covers the gap. What it needs to cover:

  • Subgrade tolerance, where the prepared surface sits slightly low across part of the area
  • Over-excavation in beam trenches, particularly in soft or wet ground
  • Formwork deflection under the weight of wet concrete
  • Pump priming and the concrete left in the line
  • Spillage, and concrete left in the truck bowl

There is no published Australian standard percentage for this, and any article quoting one is guessing. The sensible approach is to set the allowance with your supplier against the specific pour, because they know their own delivery increments, and to have the subgrade surveyed before you order rather than adding a bigger allowance to cover a pad nobody checked. Getting the subgrade and site preparation right before the pour removes most of the reason an allowance has to be generous.

Step seven: order in the supplier's units and confirm the batch

Suppliers deliver in increments, not to three decimal places. Find out the increment before you order, because it often decides your final figure more than your allowance does.

Confirm the strength grade, slump and aggregate size at the same time as the volume. A correct volume of the wrong mix is still a failed pour.

Where the pour needs a boom pump, the volume sitting in the line has to be part of the order conversation rather than an afterthought, because how the concrete gets placed changes both the pour sequence and the volume you lose to the equipment.

Why the delivered volume rarely matches the calculated volume

Boom pump placing concrete into a formed slab on a Melbourne site

Two figures exist on every pour and they are not the same number. The theoretical volume is geometry. The delivered volume is geometry plus site reality.

Inside the theoretical volume Outside it
Slab area at nominal thickness Subgrade tolerance and low spots
Edge and internal beams as drawn Over-excavation in beam trenches
Thickenings shown on the plan Formwork deflection under load
Set-downs and rebates as detailed Concrete in the pump line
  Spillage and bowl residue

Understanding which column a variance belongs in is what lets you work out whether a pour that ran over was badly calculated or badly prepared. Those have different fixes.

Common calculation mistakes that cost a second pour

  • Averaging thickness across a stepped slab. Calculate each zone separately.
  • Omitting beams entirely. The most common and most expensive omission.
  • Double counting beam intersections. Inflates the order and wastes concrete.
  • Using architectural drawings for thickness. Use the footing and slab plan.
  • Forgetting the pods work in reverse. Waffle slabs need a deduction, not just an addition.
  • Treating the pad as level. Survey it, do not assume it.
  • Ordering in bags for a structural slab. Bagged premix is for small repairs, not slabs.

Frequently asked questions

1. How do I calculate concrete for a slab?

Multiply the slab length by the width by the thickness, with the thickness converted from millimetres to metres, which gives the volume in cubic metres. Then add the edge beams, internal beams and thickenings from the footing plan, deduct pod volume on a waffle slab, and add an allowance for subgrade tolerance, formwork deflection and pump line losses before ordering.

2. How many 20kg bags of concrete make 1 cubic metre?

Cockburn Cement's published Easy Estimator puts a 20 kg concrete pack at a yield of 0.009 m³ per bag, or 110 bags per cubic metre. That figure is useful for small repairs and footing pads. For a structural slab it is academic, because the concrete is batched at a plant and delivered by the cubic metre.

3. How many wheelbarrows are in 1 m³ of concrete in Australia?

It depends entirely on the barrow. Builder's barrows vary in capacity, so the honest answer is to work in cubic metres and let the supplier deliver, rather than converting to barrow loads. Wheelbarrow figures matter only for hand placement over short distances, which is not how a slab gets poured.

4. How much does a 20x20 slab cost?

Volume is fixed by geometry, but cost is not. The rate moves with slab type, specified thickness, reinforcement schedule, site classification, access, excavation and whether steel supply and fixing are included. Two quotes for an identical 20 by 20 area can differ substantially on those variables alone, which is why what a concrete slab costs in Australia is a question about the specification rather than the area.

5. Should I order extra concrete, and how much?

Yes, order above the theoretical volume. There is no published standard percentage, so set the allowance against the specific pour with your supplier, accounting for their delivery increment, the subgrade survey, the beam depths and whether the pour is pumped. A surveyed pad needs a smaller allowance than an assumed one.

6. Do waffle pods change how I calculate the volume?

Yes, and in the opposite direction to everything else. Pods displace concrete, so you calculate the slab envelope, deduct the pod volume from the layout drawing, then add the ribs and edge beams. Applying a flat area by thickness calculation to a waffle slab overstates the pour, sometimes significantly.

Get the volume right before the truck arrives

Most pours that run short were calculated correctly and prepared loosely. The arithmetic is the easy part. The beams, the pods, the subgrade and the pump line are where the variance lives, and all four are knowable before anyone orders.

Urban Pour places reinforced concrete slabs and foundations across Melbourne. If you want the slab scope checked before it goes out to price, get in touch with the footing and slab plan in hand.

‍